PITB Capacity Building Project Plan
Project Start: Thu 02/09/04
Project Finish: Mon 21/11/05
|
ID |
Task Name |
Duration |
Start |
Finish |
| 1 |
PITB Capacity Building |
322 days |
Thu 02/09/04 |
Mon 21/11/05 |
| 2 |
Hardware and Licensed
Software Procurement |
78 days |
Thu 02/09/04 |
Mon 20/12/04 |
| 3 |
Tender Preparation
and Advertisment Release |
5 days |
Thu 02/09/04 |
Wed 08/09/04 |
| 4 |
Technical and Financial
Bids opening |
5 days |
Thu 09/09/04 |
Wed 15/09/04 |
| 5 |
Comparative statement
and PO Issue |
5 days |
Thu 16/09/04 |
Wed 22/09/04 |
| 6 |
Delivery
Period Hardware & Software
(4 Weeks- 6 Weeks ) |
28 days |
Thu 23/09/04 |
Mon 01/11/04 |
| 7 |
Inspections |
10 days |
Tue 02/11/04 |
Mon 15/11/04 |
| 8 |
Payments to the Vendors |
25 days |
Tue 16/11/04 |
Mon 20/12/04 |
| 9 |
Manpower Hiring |
78 days |
Thu 04/08/05 |
Mon 21/11/05 |
| 10 |
Advertisement preparation
and release |
5 days |
Thu 04/08/05 |
Wed 10/08/05 |
| 11 |
Advertisement Release |
5 days |
Thu 11/08/05 |
Wed 17/08/05 |
| 12 |
Application
Complilation & Short
Listings of Candidates |
25 days |
Thu 18/08/05 |
Wed 21/09/05 |
| 13 |
Interviews |
6 days |
Thu 22/09/05 |
Thu 29/09/05 |
| 14 |
Issuance of Offer Letters |
7 days |
Fri 30/09/05 |
Mon 10/10/05 |
| 15 |
Joining period |
30 days |
Tue 11/10/05 |
Mon 21/11/05 |
|