Project Description

Project Start: Thu 02/09/04
Project Finish: Mon 21/11/05
ID Task Name Duration Start Finish
1
PITB Capacity Building
322 days
Thu 02/09/04
Mon 21/11/05
2
Hardware and Licensed Software Procurement
78 days
Thu 02/09/04
Mon 20/12/04
3
Tender Preparation and Advertisment Release
5 days
Thu 02/09/04
Wed 08/09/04
4
Technical and Financial Bids opening
5 days
Thu 09/09/04
Wed 15/09/04
5
Comparative statement and PO Issue
5 days
Thu 16/09/04
Wed 22/09/04
6
Delivery Period Hardware & Software (4 Weeks- 6 Weeks )
28 days
Thu 23/09/04
Mon 01/11/04
7
Inspections
10 days
Tue 02/11/04
Mon 15/11/04
8
Payments to the Vendors
25 days
Tue 16/11/04
Mon 20/12/04
9
Manpower Hiring
78 days
Thu 04/08/05
Mon 21/11/05
10
Advertisement preparation and release
5 days
Thu 04/08/05
Wed 10/08/05
11
Advertisement Release
5 days
Thu 11/08/05
Wed 17/08/05
12
Application Complilation & Short Listings of Candidates
25 days
Thu 18/08/05
Wed 21/09/05
13
Interviews
6 days
Thu 22/09/05
Thu 29/09/05
14
Issuance of Offer Letters
7 days
Fri 30/09/05
Mon 10/10/05
15
Joining period
30 days
Tue 11/10/05
Mon 21/11/05

 
 